Task Details:
Permit Number | Site Name | Task Status | Task Type | Task Year |
C0070020 | HORIZON MINE | A | WTR | 2006 |
Task ID | Task Name | Request Date | Issue Due Date | Issue Sent Date |
2608 | WATER MONITORING | 08/16/2006 | 01/29/2009 | |
Last Updated | Updated By | Manager | Remarks By | |
08/30/2006 | SMORRISO | WHEDBERG |
Task Assignments:
Person | Assignment | Due Date | End Date | Assigned On | Assigned By | Remarks By |
DDARBY | HYDRO | 04/01/2007 | 01/05/2007 | 08/18/2006 | SMORRISO | WQ06-3 |
DDARBY | HYDRO | 07/01/2007 | 01/05/2007 | WQ06-4 | ||
DDARBY | HYDRO | 10/01/2007 | 05/03/2007 | WQ07-1 | ||
DDARBY | HYDRO | 01/01/2008 | 08/07/2007 | WQ07-2 | ||
DDARBY | HYDRO | 04/01/2008 | 03/20/2008 | WQ07-3 |
Task Activies:
Activity Date | Activity | Remarks | Added By | Date Added |
03/29/2007 | Email from Kit Pappas to PGL Re: UPDES Data for March 2007 entered in system. | PIC | ANANCE | 03/30/2007 |
10/04/2006 | Received DMRs for September 2006. | PIC | ANANCE | 10/10/2006 |
10/03/2006 | Received email from K. Pappas to DD Re: 3rd Qtr Water Data and Sept. 2006 UPDES. | PIC | ANANCE | 10/13/2006 |
11/06/2006 | Received email from Kit Pappas to Dana Dean Re: 4th Qtr Entered | PIC | ANANCE | 11/14/2006 |
12/13/2006 | Received DMRs for November 2006. | PIC | ANANCE | 12/14/2006 |
12/07/2006 | Received email from Kit Pappas to PGL Re: November UPDES Data | PIC | ANANCE | 12/21/2006 |
01/16/2007 | Received DMRs for December 2006. | PIC | ANANCE | 01/17/2007 |
06/08/2007 | Received DMRs for May 2007 | PIC | SBERRY | 06/08/2007 |
07/10/2007 | Received email from Kit Pappas to PGL Re: June UPDES | PIC | SBERRY | 07/12/2007 |
07/16/2007 | Received DMRs for June 2007 | PIC | SBERRY | 07/17/2007 |
07/17/2007 | Received email from Kit Pappas to PGL Re: 2nd Quarter Monitoring data entered | PIC | SBERRY | 07/23/2007 |
08/06/2007 | Received email from K. Pappas to PGL Re: July 2007 UPDES Monitoring | PIC | SBERRY | 08/09/2007 |
08/13/2007 | Received DMRs for July 2007 | PIC | SBERRY | 08/13/2007 |
10/05/2007 | Received August 2007 DMRs | PIC | ANANCE | 10/09/2007 |
10/08/2007 | Email from Kit Pappas to PGL Re: September 2007 UPDES | PIC | ANANCE | 10/10/2007 |
10/11/2007 | DMRs for September 2007 | PIC | ANANCE | 10/16/2007 |
03/07/2007 | Received DMRs for February 2007 | PIC | ANANCE | 03/09/2007 |
04/04/2007 | Received DMRs for March 2007 | PIC | ANANCE | 04/06/2007 |
04/16/2007 | Email from Kit Pappas to PGL Re: 1st Qtr. 2007 Monitoring | PIC | ANANCE | 04/16/2007 |
05/03/2007 | Email from Kit Pappas Re: Horizon Mine April UPDES | PIC | ANANCE | 05/03/2007 |
09/05/2006 | Received DMRs for August 2006 | PIC | ANANCE | 09/14/2006 |
02/08/2007 | Received DMRs for January 2007. | PIC | ANANCE | 02/12/2007 |
08/28/2006 | Received email from Kit Pappas to Dana D. | August 2006 UPDES monitoring has been entered | SMORRISO | 08/30/2006 |
08/28/2006 | Received email from K. Pappas to Dana Dean Re: Horizon August UPDES. | PIC | ANANCE | 09/01/2006 |
08/18/2006 | Received letter from Kit Pappas | July discharge monitoring reports | SMORRISO | 08/18/2006 |
11/08/2006 | Received DMRs for October 2006. | PIC | ANANCE | 11/13/2006 |
03/26/2008 | Email Re: February 2008 UPDES | PIC | ANANCE | 03/28/2008 |
07/16/2008 | Received email from Kit Pappas Re: June 2008 Data Entered | PIC | ANANCE | 07/23/2008 |
02/19/2008 | Received January 2008 DMRs | PIC | ANANCE | 02/22/2008 |
05/07/2007 | Received DMRs for April 2007. | PIC | ANANCE | 05/07/2007 |
11/27/2007 | Received email from Kit Pappas Re: October 2007 data. | PIC | ANANCE | 11/29/2007 |
11/30/2007 | Received DMRs for October 2007 | PIC | ANANCE | 12/03/2007 |
07/17/2008 | Received DMRs for June 2008 | PIC | ANANCE | 07/17/2008 |
09/15/2008 | Received DMRs for August 2008. | PIC, copy Dave, Jim. | ANANCE | 09/15/2008 |
09/10/2008 | Email from Kit Pappas Re: UPDES Data in the system. | PIC | ANANCE | 09/16/2008 |
04/09/2008 | Received DMRs for March 2008. | PIC | ANANCE | 04/10/2008 |
04/07/2008 | Received email from Kit Pappas Re: March 2008 UPDES | PIC | ANANCE | 04/10/2008 |
03/31/2008 | DMRs for February 2008. | PIC, copy to Dave | ANANCE | 03/31/2008 |
04/02/2008 | Email from Kit Pappas Re: 1st Qtr 2008 | PIC | ANANCE | 04/04/2008 |
05/06/2008 | Email from Kit Pappas Re: April 2008 UPDES Monitoring | PIC | ANANCE | 05/06/2008 |
05/09/2008 | Received DMRs for April 2008 | PIC | ANANCE | 05/09/2008 |
01/07/2008 | Received DMRs for November 2007 | PIC | ANANCE | 01/07/2008 |
01/16/2008 | Received email from Kit Pappas Re: December Data | PIC | ANANCE | 01/23/2008 |
01/30/2008 | Received December 2007 DMRs. | PIC | ANANCE | 01/31/2008 |
10/23/2008 | Received DMRs for September 2008 | PIC, Copy to Dave | SSTEAB | 10/27/2008 |
01/14/2009 | Dec 08 UPDES monitoring data in system | PIC | SSTEAB | 01/21/2009 |
01/16/2009 | Email from Kit Pappas Re: 4th Qtr 08 water monitoring data | PIC | SSTEAB | 01/21/2009 |
01/20/2009 | Received Dec 08 DMRS | PIC | SSTEAB | 01/21/2009 |
01/05/2009 | Received DMRs for November 2008 | PIC | SSTEAB | 01/05/2009 |
08/22/2008 | Received email from Kit Pappas Re: 2nd Qtr Data | PIC | ANANCE | 08/25/2008 |
08/22/2008 | Received email from Kit Pappas Re: 2nd Qtr Data | PIC | ANANCE | 08/25/2008 |
08/25/2008 | Received DMRs for July 2008 | PIC, copy Dave | ANANCE | 08/25/2008 |
06/27/2008 | Received DMRs for May 2008 | PIC, copy to Dave | ANANCE | 06/30/2008 |
06/05/2007 | Received email from Kit Pappas to PGL Re: May 2007 UPDES data entered | PIC | ANANCE | 06/05/2007 |
12/30/2008 | Email from Kit Pappas: Nov 08 UPDES in System | PIC | SSTEAB | 01/07/2009 |
01/29/2009 | Close out recurring task | Open task for WQ07-4 thru WQ08-4 | SSTEAB | 01/29/2009 |