Task Details:
Permit Number | Site Name | Task Status | Task Type | Task Year |
C0070042 | STAR POINT REFUSE | D | AMD | 2009 |
Task ID | Task Name | Request Date | Issue Due Date | Issue Sent Date |
3361 | CHANGE IN POST MINING LAND USE | 08/10/2009 | 11/02/2009 | |
Last Updated | Updated By | Manager | Remarks By | |
08/10/2009 | SSTEAB | JDSMITH | Work group folder created. |
Task Assignments:
Person | Assignment | Due Date | End Date | Assigned On | Assigned By | Remarks By |
DDARBY | LEAD | 11/02/2009 | ||||
ANANCE | MPMD | 08/12/2009 | ||||
ICAMPBEL | BIOL | 09/21/2009 | 08/24/2009 | JDSMITH | ||
PBURTON | SOIL | 10/06/2009 | 08/31/2009 | JDSMITH | ||
PBURTON | ADMIN | 10/06/2009 | 09/14/2009 | JDSMITH | Deficiencies |
Task Activies:
Activity Date | Activity | Remarks | Added By | Date Added |
09/16/2009 | Letter from OSM Re: MPMD | PIC | SSTEAB | 09/16/2009 |
08/10/2009 | Received Application for Change in Post Mining Land Use | 5 hard copies, 1 copy to PIC | SSTEAB | 08/10/2009 |
08/12/2009 | Email to OSM Re: MPMD | PIC | SSTEAB | 08/12/2009 |
08/13/2009 | Email from FS Re: MPMD | PIC | SSTEAB | 08/13/2009 |
08/19/2009 | Email from Lead Re: IR Completion | PIC | SSTEAB | 08/19/2009 |
08/19/2009 | Email to Operator Re: IR Approval | PIC | SSTEAB | 08/19/2009 |
08/31/2009 | 1 hard copy delivered to PFO | SSTEAB | 08/31/2009 | |
09/11/2009 | Email from OSM Re: MPMD | PIC | SSTEAB | 09/14/2009 |
11/02/2009 | Deficiency Letter & List | Mailed/Returned 11/2/09 | SSTEAB | 11/02/2009 |